文章结合天津市某基坑工程实例,介绍了插筋水泥搅拌桩的设计、施工要点和改进措施。指出:建设、设计、施工单位共同加强对4~6m浅基坑的重视,是保证此类基坑成功的关键。
|
Based on a foundation excavation project in Tianjin,the paper presents an introduction to the designs,major points of construction and measures for improvement of the cement mixing piles with inserted steel reinforcementIt is pointed out that attaching great importance jointly by the Employer,the Designer and the Contractor to shallow foundation pits from 4 m to 6 m is the key to ensure the successful completion of such projects
|
基金项目:
|
|
作者简介:
|
|
参考文献:
|
[1] GB50007-2002建筑地基基础设计规范[S].
[2] DB29-20-2000岩土工程技术规范[S].
[3] 唐业清.基坑工程事故分析与处理[M].北京:中国建筑工业出版社,2000.
[4] 基坑开挖中的岩土工程问题学术讨论会论文集[C].天津,1992.
[5] 日本CDM研究会编.水泥系深层拌和法(CDM工法)设计和施工手册[M].天津港湾工程研究所译,1991.
|