香港西区海底隧道大型钢筋混凝土沉管箱涵水下安装
作者:陶仁池 
单位:中港第一航务工程局三公司 辽宁大连 116001 
关键词:沉管箱涵  测量塔  沉放吊驳 
分类号:U459.5
出版年,卷(期):页码:2003,27(3):28-30
摘要:
香港西区海底隧道是连接港岛和九龙的第三条过海隧道,全长2km,分为三大段,即位于中间深水区的沉管箱涵段,以及位于港岛侧和九龙侧的两条引隧和基础设施段。中间隧道段长1363m,由12座113m×33.5m×8.5m,重30200t大型预制钢筋混凝土沉管箱涵构成。文中介绍了沉管箱涵安放及其相关的工程施工工艺和技术措施。
The submarine tunnel for the Hong Kong Western Harbour Crossing is the third tunnel linking Hong Kong Island with Kowloon Peninsular.The 2km long tunnel has been divided into three major sections,namely the middle section of submarine box culverts in the deep waters and the access tunnels and their infrastructure on the Hong Kong Island and Kowloon Peninsular respectively.The middle section of the tunnel is 1 363 m long,consisting of 12 sections of prefabricated large reinforced concrete box culverst with each weighing 30 200 tons and sizing 113 m×335m×85m. This paper is intended to present an introduction to the installation of submarine box culverts and the technology as well as the technical measures for the installation operations.
基金项目:
作者简介:
参考文献:
服务与反馈:
文章下载】【加入收藏
首页 编委会 理事会 期刊检索 过刊浏览 广告合作 联系我们 EngLish

津ICP备11001124号-2
《中国港湾建设》编辑部     地址:天津市河西区大沽南路1002号
电话:(022)28348642   传真:(022)28348642 
邮箱:zggwjs@126.com    邮政编码:300222