重力式沉箱码头干法施工在实际工程中应用较少,与水下安装预制结构的湿法施工相比,干法施工具有施工过程透明、施工精度高、施工进度快等优点。文章以国家重点工程项目烟台至大连铁路轮渡工程项目为例,提出干法施工的工程可行性与施工技术措施。
|
Dry construction was rarely used in construction of gravity caisson quay-walls.Compared with the method of wet construction,dry construction has an edge over the latter in terms of its transparency in construction,precise engineering and relatively shorter construction period.In this paper,the author,using the National Key Project-Railway-Ferry Terminal between Yantai &Dalian,as a case,illustrated the feasibility of application of the technique in actual engineering practice and also suggested technical measures that could be adopted in actual engineering practice.
|