改形方块与陆上推进法在斜坡堤施工中的应用
作者:王成环 
单位:京唐港务局 河北唐山063611 
关键词:斜坡式挡沙堤  改形方块  陆上推进法 
分类号:U656.21
出版年,卷(期):页码:2002,26(4):12-14
摘要:
京唐港斜坡式挡沙堤 ,用陆上推进法施工的“高胖堤”,反而比用水上法施工的“矮瘦堤”造价低。将堤顶“四脚空心方块”改为“改形方块”,实施“改形方块与陆上推进法相结合的工艺”,不但能使堤及时封顶 ,风损小 ,工期短 ,航道回淤小 ,更能适应堤的多次延伸调整
The construction of a "high but plump mole" proceeded from the land side cost less than a "short but slender mole" proceeded from offshore when a rubble mound sand arrester mole was built in Jingtang Port. The armour blocks were modified form "tetrapod hollow blocks" to "hollow square blocks" and the construction method was a procedure to combine the modified blocks with works proceeding from the land side. By so doing, the mole was timely completed with a short construction period, less wind caused loss, little siltation in the navigational channels and more adaptable to the extensions and changes of the mole.
基金项目:
作者简介:
参考文献:
服务与反馈:
文章下载】【加入收藏
首页 编委会 理事会 期刊检索 过刊浏览 广告合作 联系我们 EngLish

津ICP备11001124号-2
《中国港湾建设》编辑部     地址:天津市河西区大沽南路1002号
电话:(022)28348642   传真:(022)28348642 
邮箱:zggwjs@126.com    邮政编码:300222