锦州港码头胸墙产生较大偏位的初步分析
|
作者:张华玉 |
单位: 一航局五公司 |
关键词: |
分类号: |
出版年,卷(期):页码:1991,15(6):47-50 |
摘要:
|
锦州港杂货码头在施工中胸墙产生了较大的偏位。本文根据实测数据及有关施工资料进行分析,认为胸墙产生较大偏位的主要原因是在码头沉降和位移尚未稳定的情况下,过早地进行码头胸墙施工所致,同时也受基础工程夯实质量不好等不利因素的影响。
|
The parapet of general cargo quay in Jinzhou port deflected considerablly during construction period. The paper, based on the in—situ measurement and construction recordings, carried out an analysis, and concluded that the main reason caused such deflection was that the eonstruetion of quay parapet was started too early before the settlement and displacement of quay structures reached stable. Besides, the compacting quality of the foundation was not good enough etc.
|