通过对天津港软土地基加固工程实测资料分析,探讨了沉降修正系数、固结系数以及理想井与非理想井的差别,分析了真空预压排水板间距、预压加固时间与加固造价的关系,得出的几点认识供工程技术人员参考。
|
Based on the analyses of the measured data on the soft soil improvement projects in Tianjin Port,thecorrection coefficient of settlement,coefficient of consolidation and the difference between ideal wells and non-idealwells are discussed.The intervals of fabricated drains for vacuum preloading and the relationship between the timeof consolidation and the cost of soil improvement are analyzed.Some understandings are achieved for the referenceof the engineering and technical personnel.
|