隧道浅埋段施工技术
作者:杨文平 刘新立 周大兵 
单位: 
关键词:浅埋 超前支护 超前地质预报 监测 
分类号:
出版年,卷(期):页码:2012,40(2):55-59
摘要:

以新建山西中南部铁路通道工程秦家凹隧道浅埋段施工为实例,从重点控制超前支护、开挖、支护、仰拱
监控量测和超前地质预报等几个方面对浅埋段施工技术进行阐述,合理调整开挖和支护参数,集中体现隧道浅埋施
工应遵循“管超前、短进尺、强支护、早封闭、勤量测、及时衬砌”的原则,有效地保证了隧道的安全、快速掘进,
为后续的浅埋段和同类工程提供经验和借鉴。

Take the construction of the new shallowly buried section of Qinjia忆ao Tunnel in the railway project at Central
South of Shanxi as an example,this paper describes the construction technology for the shallowly buried section from the key
control of pre-support,excavation,support,monitoring and measurement of inverted arch,and advance geological fore原
cast, etc.,and rationally adjusted the excavation and supporting parameters,the shallow buried construction of tunnel should
follow the principle of “pipe in ahead, short drilling footage,strengthening the support,early closing,frequent measure原
ment, and timely lining”,effectively ensuring the safe and speedy building of the tunnel and providing experiences and refer原
ences for the follow-up shallow buried sections and similar projects.

基金项目:
作者简介:
参考文献:
服务与反馈:
文章下载】【加入收藏
首页 编委会 理事会 期刊检索 过刊浏览 广告合作 联系我们 EngLish

津ICP备11001124号-2
《中国港湾建设》编辑部     地址:天津市河西区大沽南路1002号
电话:(022)28348642   传真:(022)28348642 
邮箱:zggwjs@126.com    邮政编码:300222