港珠澳大桥埋置式承台基坑冲淤试验研究
作者:仇正中 吴启和 牛照 
单位: 
关键词:港珠澳大桥 淤泥质海岸 埋置式承台 超挖深度 减淤措施 
分类号:
出版年,卷(期):页码:2013,33(1):25-28
摘要:

依托港珠澳大桥埋置式承台足尺模型工艺试验项目,采用理论计算分析与原位试验监测相结合的办法对埋
置式承台基坑超挖深度进行研究。理论计算分析采用海港水文规范经验公式进行估算,原位试验采用单波束测深仪
定期和不定期对试验基坑开挖后水下地形进行测量,在此基础上,提出适宜的承台基坑超挖深度,为港珠澳大桥主
体工程建设关键施工参数的确定提供依据。

Relying on the full-scale model test of embedded pile capping for Hong Kong-Zhuhai-Macao Bridge,the method
combining theoretical calculation analysis with in-situ monitoring tests is used to study the over-dredged depth of foundation
excavation. In the theoretical calculation estimate,an empirical formula of the Hydrology of Sea-port is adopted for the overdredged
depth, while the single-beam is for the topographic survey underwater at random after the foundation excavation in the
in-situ monitoring test. On that basis,proper over-dredged depth of pile cap foundation excavation is put forward to provide
key construction parameters for the main works of Hong Kong-Zhuhai-Macao Bridge.

基金项目:
作者简介:
参考文献:
服务与反馈:
文章下载】【加入收藏
首页 编委会 理事会 期刊检索 过刊浏览 广告合作 联系我们 EngLish

津ICP备11001124号-2
《中国港湾建设》编辑部     地址:天津市河西区大沽南路1002号
电话:(022)28348642   传真:(022)28348642 
邮箱:zggwjs@126.com    邮政编码:300222